Stop Financing Your Customers’ Jobs: Contractor Cash Flow Lessons from a 23-Year-Old Deck Builder

Here’s how most contractors pay for jobs:

Take the deposit from the last job. Use it to cover materials on this job. Hope the next deposit lands before the credit card bill does.

“That’s what like 95% of everyone does,” said Jake Andrews from Level’s tax team.

Then he told us about a 23-year-old who figured out how not to.


The deck builder who’s cash-flow positive in year one

Jake recently talked with a young deck builder who’s been cash-flow positive since year one and is aiming for $5 million in revenue next year. His system isn’t complicated:

1. He charges for every estimate

Even a small one, around $2,000, collected before he walks the job, measures, and prices it.

“Everyone’s giving free estimates for hours they’re wasting walking around and measuring,” Jake said. “Why? You should bill for that time. And you’re going to get better customers. You won’t get the cheapskates trying to skimp on everything.”

2. He uses a 30 / 30 / 30 / 10 payment schedule

The customer pays in four installments tied to project phases. By the time he’s finished the first two or three phases, he’s collected close to half the job or more.

3. He puts materials on a card and pays it on the due date

Materials for the job go on a credit card. He collects the customer’s progress payments, then pays the card off on the last possible day, in full, every month.

The result: “He’s not actually spending any money for 60 days. He’s just collecting,” Jake said. “He’s not digging into his own pocket for anything, and he’s covering all his overhead.”

The point isn’t the credit card. It’s the order of operations: customer money comes in before your money goes out. The card just gives you float. Carrying a balance and paying interest defeats the purpose.


Why are you the one fronting the cash?

Jake: I want to send that clip to every client who’s financing jobs for customers. Why are you borrowing money to finance a job? The customer wants the pool. They want the addition. Why are you the one fronting the cash? It doesn’t make sense, but people do it.

If you regularly use a line of credit to buy materials or make payroll while customers pay you later, you’re running a free bank for your customers. Fixing it starts with three things:

  • Deposits on every job (held properly, see How to Handle Customer Deposits)
  • Progress billing tied to phases, not one invoice at the end
  • Payment due on completion, not “net 30” by default

When the GC is the problem

Private customers are one thing. Subcontracting for general contractors is another.

Katie described what a specialty subcontractor she knows deals with constantly: on residential jobs (not commercial), the GC says, “Submit a bill, and if we approve it, we’ll pay you in 45 to 60 days.”

“So he has to come out of pocket,” she said. “There’s $1,000 in the bank account, and he has to put $20K on a credit card. You’re the GC. You’re collecting this money from the customer. Pay it out. Stop expecting us to cash-flow your jobs.”

The contract we red-lined

Then she pulled out a GC’s subcontract. Here’s what was in it, in plain English:

  • Risk of loss: the sub is responsible for theft or damage to its own work and materials until “final acceptance,” and for protecting the owner’s property and other trades’ work.
  • Payment timing: pay applications received between the 1st and 20th get processed for payment on the 15th of the following month, roughly 45 days. Applications received after the 21st are rejected and have to be resubmitted the next month.
  • Pay-if-paid: the GC only owes the sub if and when the GC gets paid by the owner, “as an absolute condition precedent.” The sub assumes the full risk of the homeowner not paying, even though the GC hired them.
  • Lien waivers before payment: the sub has to sign conditional and unconditional lien waivers, for itself and every supplier below it, before getting paid.
  • Withholding: the GC can hold back payment for almost anything, including “reasonable doubt as to timely completion” or “unsatisfactory prosecution of the work.”
  • Change orders: the GC decides what they’re worth.

“That must mean nobody reads these and just signs them,” Jake said.

They didn’t sign it. They sent back an addendum with the terms they’d agree to. “We’re too small to lose 50 grand,” Katie said.

What to look for in any subcontract

Before you sign, find these clauses and have them reviewed:

ClauseWhy it matters
Pay-if-paid / pay-when-paidDecides whether the GC’s customer problem becomes your problem
Payment timing and cutoffs45–60 day terms turn you into the GC’s lender
Unconditional lien waiversNever give up your lien rights before the money clears
Withholding rightsVague terms (“unsatisfactory”) can mean “whenever we want”
Change order pricingYou should agree on the price before doing the work
Risk of lossYou shouldn’t insure other trades’ work

Level note: We’re accountants, not attorneys, and rules on pay-if-paid clauses vary by state. Have a construction attorney review any subcontract you’ll sign more than once. It’s cheap compared to one unpaid job.


Another fix: get on site and run it yourself

Jake mentioned a friend who owns an electrical contracting company and deals with the same thing:

“He’s basically a GC. He goes to the job site and manages the job himself, so he doesn’t lose money when he sends his guys there. They say, ‘Just come back in two or three days and finish.’ And he’s like, no, I’ve got four guys here, we’re finishing today. I’m not wasting that time.”

Every return trip is labor you’re not billing for. Some subs keep those GC relationships and build return trips into their price. Others walk away.


The takeaway

Cash flow problems usually aren’t revenue problems. They’re timing problems:

  • Charge for estimates
  • Collect deposits and progress payments that stay ahead of your costs
  • Use supplier and card terms to your advantage, and pay in full
  • Don’t sign contracts that make you the bank

Profitable on paper but always short on cash? We’ll look at your payment terms, AR, and how deposits are handled. Book a call with Level →

General education, not legal or tax advice for your specific situation.

subcontractor packet for contractors. collect W9s, workman's comp insurance, general liability insurance

FREE RESOURCE

The Subcontractor Packet That Protects You From a $30K Audit Surprise

-> The complete done-for-you packet — setup form, W-9, and sample subcontractor agreement ready to hand to every sub before their first check

-> The one missing document that lets your insurance company add a sub’s entire payment to YOUR workers comp premium — and how this packet prevents it

-> The insurance minimums, COI requirements, and indemnification language most contractors don’t have in writing until it’s too late